Site requirements  4 

Site requirements 

About this document 

This document outlines the instal ation requirements for a 6 m (20 ft) HP POD. These guidelines are for a 
qualified architectural or consulting engineering team to generate site-specific documents for each HP 
POD installation. The site-specific installation documentation must comply with local building code 
jurisdictions. 

 

Site preparation 

The HP POD must be installed on a surface capable of supporting approximately 24,948 kg (55,000 lb). 
The site location for the HP POD must be level +/- 0.5 degrees tolerance. Appropriate clearance for 
instal ation, service, and system utilities (power and water) must also be considered. 

  

 

IMPORTANT:  Before installing the HP POD, consult your local AHJ for applicable codes and 
to review site-specific location guidelines. 

  

  

 

IMPORTANT:  The HP POD is designed for ground level installation. If you install the HP POD 
on an elevated surface, make sure the minimum height requirements for circuit breaker 
actuators are considered per local and national electric code requirements. 
The area in front of the outside panels must include a work platform. The distance from the 
work platform surface to the center of any circuit breaker actuator handle must not exceed 
183 cm (72 inches). The platform must be a minimum of 91 cm (36 inches) wide for free air, 
and if the platform construction is grounded metal, must be a minimum of 107 cm (42 inches) 
wide. 

  

 

Safety information 

The HP POD is certified to UL 69050/IEC 60950 as an Information Technology Product and Classified 
according to the National Electric Code NFPA-70, 2008 
The HP POD is not suitable for long term human occupancy. The HP POD has service access areas for 
periodic maintenance and service. These areas must be used only by owner-authorized personnel who 
are trained in the maintenance and service of the HP POD IT components. 

  

 

IMPORTANT:  Before installing the HP POD, consult your local AHJ for applicable codes and 
to review site-specific location guidelines. If needed, obtain any necessary permits. 

  

Before installing your HP POD, verify that the following prerequisites have been met: 
•  All components have been delivered to your facility. 
•  The HP POD, power distribution components, and water distribution components are in their final 

location. 

•  You have facility power at your final location. 