Environmental considerations  20 

Environmental considerations 

Environmental risks 

  Avoid placing the HP POD 20c directly along a drainage path or in an area prone to flooding. 

  Verify that the HP POD 20c is properly grounded in accordance with national, regional, and local 

regulations, ordinances, codes, and the product specifications. 

 

Cold weather 

The HP POD 20c requires a site chil ed water supply and return, humidifier supply and drain, and 
condensate drains. Extreme cold weather can cause damage to the supply and drain lines. Evaluate the 

following for additional cold weather protection: 

  Regional location of the HP POD 20c 

  Exposure of the supply and drain lines to extreme cold temperatures 

Extreme cold weather can affect crane and lifting operations. When temperatures drop below -12.2°C 

(10°F), appropriate consideration must be made with respect to shock loading, crane hydraulics, and 

possible de-rating of the crane. 

 

Areas prone to lightning or power surges 

The HP POD 20c structure and internal components are all bonded together. A common Grounding 
Electrode Conductor Connection point is provided. Proper bonding and grounding of the HP POD 20c 

minimizes the effects of a lightning strike. A surge protection device is provided on the HP POD 20c input 

connection to protect the HP POD 20c electrical system from voltage transients. If your site is in an area that 

is subject to frequent lightning strikes, the HP POD 20c must be protected in accordance with NFPA 70 (NA) 
and IEC (EMEA and APJ). HP recommends that you contact a certified lightning protection consultant. 

 

Seismic activity 

If your site is in an area that has frequent seismic activity, HP recommends that you contact a seismic activity 

consultant. If your site is in an area that has high vibration level, HP recommends that you contact a vibration 
isolation consultant. You must specify the method of anchoring the HP POD 20c, if necessary. 

0.522245s